The following is a list of road projects that are on the Kentucky Department of Transportation six year road plan through 2012 for Floyd County.
Majority of the list are bridge replacements.
The total amount is $ 6.2 million
Replace bridge at Bosco and approaches at Right Fork Beaver Creek $ 750,000
Replace bridge at Left Fork of Beaver Creek at Drift $ 1.4 million
Replace bridge at Cow Creek $ 1.075 million
Replace bridge over Brushy Creek at Floyd/ Pike Line $ 700,000
Replace bridge on KY 466 over Left Fork Beaver Creek $ 1.75 million
Replace bridge on KY 777 over Right Fork Beaver Creek $ 1.2 million
Reduce curve on at KY 680 intersection at McDowell
Reconstruct Holiday Hill on US 23 $ 500,000.
Majority of the list are bridge replacements.
The total amount is $ 6.2 million
Replace bridge at Bosco and approaches at Right Fork Beaver Creek $ 750,000
Replace bridge at Left Fork of Beaver Creek at Drift $ 1.4 million
Replace bridge at Cow Creek $ 1.075 million
Replace bridge over Brushy Creek at Floyd/ Pike Line $ 700,000
Replace bridge on KY 466 over Left Fork Beaver Creek $ 1.75 million
Replace bridge on KY 777 over Right Fork Beaver Creek $ 1.2 million
Reduce curve on at KY 680 intersection at McDowell
Reconstruct Holiday Hill on US 23 $ 500,000.